storage location mrp indicator

dear experts

I have a problem about mrp.

Our mrp has a one plant P100, storage location A, B.

storage location B is on-site location by shop floor.

storage location A is a warehouse.

we set the material master like following because we want to keep some stock level at storage location B.

Storage location B is set Sloc MRP indicator 2(Storage location stock planned separately) and reorder point qty about some material master in mrp 4 view storage level.

So storage location B is provided with some material from storage location A when material stock in B is under reorder point.

if some material's requirement is 100 and B has 100 stock and A has no stock, after mrp run, 100 PR is created. this is our problem.

i don't want to be created procurement requisition at location A.

In other words, when mrp runs, i want to include location B's stock.

is it possible?

thanks in advance.



No, it is not possible to define a storage location as planned separately and also consider this stock at plant level when running MRP.

This is not possible and your business requirement does not make sense to me. You have mentioned that you have defined this storage location as planned separately because you want to keep some stock under storage location B, therefore, why do you want to consider this quantity when running MRP? MRP would consider this quantity, a replenishment proposal would not be created and you would end up without stock on storage location B.

Can you please explain exactly what is the expected system behavior?