Asynchronous Processing of Workflow in Final Step Pro's and Cons?

Former Member
0 Kudos


Hi,

I was wondering if anybody has experience with "Asynchronous Processing of Workflow in Final Step".

in our workflow process we have decided to use Decision type 4:  item based desicion for partial document.

currently we are working on SRM Server 731 and I cannot find this in customization. I suspect I need to enable business function : SRM_APF_IMPR_1.

can any body confirm this?

But does anybody have some experience using this functionality, and provide some experience in the Pro's and Con's.

on the link i found on SAP website limited information is available: :

http://help.sap.com/saphelp_srm701/helpdata/en/c9/e6c2d976564cfe83ba850890d6f946/frameset.htm

Hope anybody can provide some insight.

thanks Sing

Accepted Solutions (0)

Answers (2)

Answers (2)

konstantin_anikeev
Active Contributor
0 Kudos

Hi Sing,

SAP says, that asynchronous processing should be faster for the large shopping carts (Last approver should not wait to long). But actually I have not determined big difference.

If you activate this switch - do not fordet to activate following entry in SWE2.

Regards

Konstantin

laurent_burtaire
Active Contributor
0 Kudos

Hello Sing,

yes, you have to activate Business Function (reversible) SRM_APF_IMPT_1 to get customizing switch ID SRM_701_APF_ASYNC_PRC_FINISH in IMG .

I cannot give you a feed-back for this switch as i never used it...

Regards.

Laurent.