Hello All,
In subcontracting scenario.
The Schedule delivery date in SA for Parent material is 12.03.2015 with quantity 400. But requirement date for child part was 24.02.2015 with 400 quantity.
I have checked following points.
Kindly help me out to overcome this issue.
Regards,
Manoj
Hello Manoj,
Requirement date is always calculated as follows: first, the planned delivery time (in calendar days) is deducted from the delivery date
So the requirement date = delivery data in the PO - planned delivery time - Purchasing processing time in working days (T-Code OPPQ).
If the planned delivery time deviates in the info record from the delivery time in the purchase requisition, the planned delivery time of the info record is preferred.
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
The requirement date generally is generally the order/requisition start date. Since it is a subcontracting scenario, the order start date is calculated according to the planned delivery time.
Try to change the PDT on the requisition and run a new BOM explosion.
BR
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.