on 03-24-2015 7:31 AM
hello,
We are getting below error at APO, when run CCR, please help us to correct.
Message no. /SAPAPO/CIF575
Operation 0020 for order 000000160808 has the following differences between SAP APO and SAP R/3 for the setup group:
i checked setup goup at master recepie
at general data of operation..>>>>Setup family>> Goup = 1.
At APO tcode CDPS_setup, user udpated against Location & setup matrix
predecessor setup group, successor setup group, setup time - 8 & Unit - H
Kindly help to resolve inconcistancy at CCR report.
Thanks in Advance.
We are not getting error at CCR, but some time process order missing operaions at RRP3 and just showing activity udpated with order.
If we do change source of supply, then operations udpated correctly. but it is just workaround we need to find root cause of why operations are missing.
We asked client to udapte setup matrix as they updated setup group at master recipe, Do you think this will help us to correct issue?
Regards,
Nilesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Nliesh,
Are you converting planned order in ECC or APO?
Also check the activity relationships are maintained in R/3 correctly
Are you getting message any message like /SAPAPO/RRP159 operation setup activity is missing?
Please refer the SAP help document,
Best Regards,
R.Brahmankar
Thanks brahmakar,
I updated setupmatrix and issue resolved
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for Answer brahmakarI dont want to maintain setgoup inforamtiona at APO.
But my first phase have setup group 1 updated as a default APO.
What will impact if I have not updated setup goup information at APO?
Kindly help.
Thanks,
Nilesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Nilesh,
This could be due to
In ECC recipe, maintain the setup group information for the other phase also
In APO system, in TA /SAPAPO/CURTO_SIMU, the production data structure(PDS) contains the operation xx which has setup group assigned for setup phase as well as produce phase.
In APO system check the production data structure(PDS) in TA /SAPAPO/CURTO_SIMU
Transfer the process order from ECC to APO from CCR.
Please refer OSS note
759343 - Delete setup groups information in APO if not in R/3
Also refer this discussion,
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
15 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.