on 03-23-2015 11:15 AM
Hi Gurus,
I am facing a problem with our SRM portal. We need to be able to redistribute the shopping carts more than once to a purchaser group (e.g.due to the absency of a purchaser). For this, we tried to implement the BADI BBP_SC_PGRP_ASSIGN, Method for Purchasing Group Assignment of Requirements. Is this possible using this BADI? If not, which method would be adequate?
Thank you in advance,
AB
Message was edited by: Zoltan Keller
Hi
Yes you can assign multiple times if you use the Workload redistribution Functionality.
SAp suggested the below reason .. for the same ..which matches your requirement
Documents may have to be manually assigned for the following reasons:
If you do not maintain the assignment rule, documents are assigned to a default purchasing group that has to be processed manually.
Refer the links as below as well for your reference :
Workload Distribution - SAP ERP 2005 SAP SRM - SAP Library
http://help.sap.com/saphelp_srm70/helpdata/en/45/f12b3c7e4b60d4e10000000a11466f/content.htm
Regards
Vinita
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
as Laurent already written - not possible.
If your Purchaser is absent - you can use standard functionality of "Workload Redistribution"
Regards
Konstantin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
this is not possible as only one purchasing group can be assigned to a SC item (BBP_PDORG table).
Regards.
Laurent.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.