on 03-19-2015 1:57 PM
Hi,
Is it possible to set the day's supply in workdays in RRP3?
Thanks.
Regards.
OCS
Hello Oscar,
Use BADI /SAPAPO/RRP_COVPARAM (From SAP Note 1027082) to influence the results of Day's Supply calculation
The /SAPAPO/RRP_COVPARAM BAdI only takes the calendar into account when the days' supply is calculated. It can be used for flexible calculation of the days' supply in the product view.
Also refer SAP Note 970081 - The Days' Supply/receipt is not shown according to calendar
Best Regards,
R.Brahmankar