ASN processing compulsory?

Former Member
0 Kudos

Hi everyone,

is it possible to use scheduling agreement releases in SNC without ASN processing? 

One of our suppliers wants to get the schedule releases only for display purposes on SNC. He is not to be out to create ASNs.

We expect to get problems with the due quantity calculation. Does anybody have some experience with that?

I would be grateful for your answers.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi An Chi,

It is possible.

Go to transaction code:/N/SCA/ORDER_CFG and then go to Set Confirmation control

Maintain below settings:

Order Type=Scheculing Agreement Release

Supplier= Supplier BP

Conf.by.ASN=Not allowed

Regards,

Nikhil

Former Member
0 Kudos


Hi Nikhil,

thank you very much!

Regards,

An Chi