Hi everyone,
is it possible to use scheduling agreement releases in SNC without ASN processing?
One of our suppliers wants to get the schedule releases only for display purposes on SNC. He is not to be out to create ASNs.
We expect to get problems with the due quantity calculation. Does anybody have some experience with that?
I would be grateful for your answers.
Hi An Chi,
It is possible.
Go to transaction code:/N/SCA/ORDER_CFG and then go to Set Confirmation control
Maintain below settings:
Order Type=Scheculing Agreement Release
Supplier= Supplier BP
Conf.by.ASN=Not allowed
Regards,
Nikhil