Vendor Delivers products only on Friday

Former Member
0 Kudos

Hello,

We have scenario where we do subcontracting as well as purchasing. Now some vendors sends delivery of the products on some specific days like only on Friday or Monday etc.

Our requirement is to cater this constraint such that the purchase requisition created by heuristics will take this constraint into consideration and show the delivery date as per the constraints e.g. it has delivery date of only Fridays for Vendor A who delivers products only on Friday.

What  are the settings required to do in APO side as well as in ECC side.

Accepted Solutions (0)

Answers (2)

Answers (2)

UmeshMali4994
Active Contributor
0 Kudos

Hello Nilesh,

You can achieved your requirement in ECC through planning calendar calculation rule,

Go through below document of Planning calendar calculation rule 

For APO side you can achieve through time stream calendar in APO as Mariano suggested.

I hope this information helpful to you

Regards

Umesh Mali

marianoc
Active Contributor
0 Kudos

Hello,

You can create a time stream calendar in APO (it should have only Fridays) and then you can assign it as the plannig calendar of your material (/SAPAPO/MAT1 --> Lot size view).

You can do something similar in ECC, creating a planning calendar, but if the order is created in APO, then do not worry about ECC.

Kind Regards,

Mariano

Former Member
0 Kudos

Thanks for reply Mariano,

I am using Planning Calendar with Shipping on Friday. What happens is when Heuristics is run and PurReq created it shows in Product View as Start Date (Which is Delivery Date in PurReq) as 04.05.2015 and the Availability Date as 08.05.2015 (Friday).

What we want is to have in Product View Start Date to show as 08.05.2015 which is Friday.

Currently System is taking into account the GR Processing Time of 4 Days.

Product View below Shows Start Date 04.05.2015 which is Delivery Date in ECC above

Please revert what is missing.

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello Nilesh,

GR processing time is used in the scheduling.

Availability date = Delivery date + Goods receipt processing time


What we want is to have in Product View Start Date to show as 08.05.2015 which is Friday.

In this you need to remove the GR processing time from product master.

Please refer OSS note 1822406 - Availability date and GR processing time in R3 and APO

Best Regards,

R.Brahmankar