on 03-17-2015 3:00 PM
Dear Experts,
Kindly help me to find the RFx Technical Opening Date and RFx Price Opening Date if we have not maintained it in RFx during creation.
If we don't mention any Rfx Opening Date & Time then we can perform this activity anytime after submission deadline.
After some analysis I found that same can be found with the combination of Tables /SAPPSSRM/SLBH & TBTCO.
/SAPPSSRM/SLBH stores all simultaneous login batch process details and TBTCO stored the other details of batchjob.
Issue:
For some of the entries in /SAPPSSRM/SLBH I am not able to find records in TBTCO.
Kindly suggest any way to find the Date and Time in this case.
Thanks
Rajan
Dear Experts,
Kindly suggest any way to find out the actual RFx Technical/Price Opening Date. How we can find out the date when Simultaneous Logon activity is performed?
Thanks
Rajan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.