Hi All,
We use KP26 to maintain plan values against cost centre and activity and this is used on a project/network plan costs, we then change the rate in KP26. To update the project/network we go into transaction CJ20n -edit-costs - calculate costs - is there transaction to update the new rates on all projects? rather than going into each project and updating each project.
thanks
Joe
Hi Joe,
You can run mass network costing with CJ9K.
Regards,
Paulo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Joe,
Reconstruct to all project through CJBN after pricing update by KP26. it will get updated with new update.
Regards.
Sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.