Update plan rates on Project/Network

former_member355038
Participant
0 Kudos

Hi All,

We use KP26 to maintain plan values against cost centre and activity and this is used on a project/network plan costs, we then change the rate in KP26. To update the project/network we go into transaction  CJ20n -edit-costs - calculate costs - is there transaction to update the new rates on all projects? rather than going into each project and updating each project.

thanks

Joe

Accepted Solutions (1)

Accepted Solutions (1)

Paulo_Vitoriano
Active Contributor
0 Kudos

Hi Joe,

You can run mass network costing with CJ9K.

Regards,

Paulo

Answers (1)

Answers (1)

sanjeevc
Active Contributor
0 Kudos

Hi Joe,

Reconstruct to all project through CJBN after pricing update by KP26. it will get updated with new update.

Regards.
Sanjeev