hello Experts,

we have promoted,successfully, our application (developed on Design studio dev ) to Production environment .

The promotion status shows success and we can see the application on Prod Design studio as well.

But the application is not working on Prod , as the data source reallignment did not happen automatically. So the DataSource of the Design Studio Application is still pointing to our SAP BW Dev system instead of our SAP BW Production system.

We already configured the override settings but it didn't help so far.

could you please help me to resolve/pin point the issue here.

thanks ,

vinay singh


Hi Vinay,

    For the First time, if you are moving Design studio Application and if Connection is not there in Production with whcich Design studio Application got created then move both Connection and Design studio Application.

       And once connection moved change the Connection Details in Production to point to Production Bex Source (In OLAP Connection).

      Or if Connection is already moved or its there, then move only Application.

       Prior to all Bex queries need to be moved first from Production to Development.