Work center confusion

Hi Gurus,

I have one scenario.

For one finished product they are using 100 moulding machine on rotation basis. That is their business process flexibility, that as per their requirement and availability they can go for any moulding machine. So how i ll make work center and how that will assign in routing?

How scheduling will be carried out?

Please help me...

Thanks in advance!!!





Create a work center category as Machine and in capacity header you can define number of individual capacities as 100.

You would be having available capacity as individual moulding machine running time multiplied with number of individual capacities.