Hi,

I have one query ,We are using classic Scenario in which user is creating a SC based on Asset + WBS element but PO get created with Internal + Asset + WBS. now user trying to GR/Confirmation as there is wrong in the process ( I.e., where the Order not come in to the picture) he cannot proceed further.

Thanks & Regards,

Pramod.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Pramod,

In Asset master(ECC), internal order should be maintained.

So the system populate internal order in the PO for asset.

Please check with your FI consultant.

Regards,

Vishnu

Former Member
0 Kudos

Hi Vishnu,

I checked it in Asset master its not working.So please help if you can.

Thanks & Regards,

Pramod.