First Posting Date wrongly entered

0 Kudos

Hi,

During contract creation(RECN) first posting date has been entered wrongly as 31.03.2015 instead of 01.12.2014.

Concern is that system automatically posted the document on 01.02.2015.Unable to reverse it,neither it is deactivated nor deleted.

We have to entered the correct date in first posting date field but it is not editable.

Is there any way to bring it into editable mode or any other way??

your reply will be highly appreciable.

Thanks & Regards

Md Rizwan

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

As Bowen said that either you can change the data in the Standard table itself or you can change the date by using FM:- BAPI_RE_CN_CHANGE.

Execute this FM with the relevant details and commit it then the FM will change the data in the contract and in table.

Hope it will help you.

Regards,

Sid

bowen_cao
Contributor
0 Kudos

Hi,

There is no standard way to change the first posting date, since you have already posted some cash flow and not able to reverse, I would suggest you to change the value in tables directly.

Regards,

Bowen