on 03-11-2015 9:42 AM
Dear Experts,
Have set MRP batch job. Most of the materials marked with MRP type VB are not planned. I checked by running MRP manually via MD03
and even by activating planning file entry , Even still the material is not getting planned even
foreground nor even background .
Note : For some of the Materials which MRP has happened for first time , it has created PR properly.For most of the materials , with the below example
displayed they are not planned correctly.
In the below example , last MRP data is shown . why system is not taking these material into considerations..?
Re-order point -100 , Max stock level is 500 .
If i re run MRP system should revise the PR for 15 + 485 (instead of 300) = 500
I have re run the MRP via MD03 checked even by maintaining planning file entry.
with regards,
Hello Daya,
I can see the PR is firmed could you please deleted it and rerun the MRP.
You should have a Purchase Requisition or Planned Order for a quantity to take stock up to maximum level (as was spesified in material master).
Please refer SAP help link,
Replenishment up to Maximum Stock Level - Consumption-Based Planning (MM-CBP) - SAP Library
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
SAP Daya,
Please note firmed planned orders/purchase requisitions would not get deleted by MRP even though you run MRP with planning mode 3.
You need to delete the existing firmed PR and Re run the MRP which creates procurement proposals as per your expectations.
BR
KK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.