Reg: MRP for CBP Materials

Dear Experts,

Have set MRP batch job. Most of the materials marked with MRP type VB are not planned. I checked by running MRP manually via MD03


and even by activating planning file entry , Even still the material is not getting planned even


foreground nor even background .

Note : For some of the Materials which MRP has happened for first time , it has created PR properly.For most of the materials , with the below example


displayed they are not planned  correctly.

In the below example , last MRP data is shown . why system is not taking these material into considerations..?

Re-order point -100 , Max stock level is 500 .

If i re run MRP system should revise the PR for 15 + 485 (instead of 300) = 500

I have re run the MRP via MD03 checked even by maintaining planning file entry.

with regards,

CBP(1).png (32712 B)
CBP(1).png (32712 B)
Former Member
replied

Hello Daya,

I can see the PR is firmed could you please deleted it and rerun the MRP.

You should  have a Purchase Requisition or Planned Order for a quantity to take stock up to maximum level (as was spesified in material master).

Please refer SAP help link,

Replenishment up to Maximum Stock Level - Consumption-Based Planning (MM-CBP) - SAP Library

Best Regards,

R.Brahmankar