on 03-09-2015 1:10 PM
Hi ,
We have requirement in our company that when a production order is 30 days old , it should automatically completed technically .
How to set up this background job.
Thanks.
Dear crazy,
you could create a run variant in COHV t-code in mode (Techcally complete)
and in this run variant you can use the selection dates ( relative with +30 and -30 days).
After that you must create a job (sm36 ) with
program : PPIO_ENTRY
and run variant just created
I hope have been useful for you
Let me know if this soluction work for you
Daniele
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Daniele,
What is the purpose of providing the negative values ? Will this technically completed orders which are ( for eg released ) 30 days back ?
Above you have mentioned selection dates +30 and -30 days ? Are these days you are taking about from the selection screen in the COHVPI report?