MP Next Call Date

Dear Experts,

Could you please help me to get the Table for next call date of Maintenance Plan.The scenario is given below.

1.I have one Maintenance Plan if i am seeing the call date in IP19 it shows me the Call No. e.g. 1 to 7 (Because it refresh IP10)

2.If i am seeing in IP24 it shows only 1 to 6 Call because it does not refresh IP10.Call No. 7 is Missing because i haven't refresh IP10.

May i know the Table where i can get a similar Calls (1 to 7) as mentioned in point No. 1.

Thank You,




Hi Raj,

MHIS will not be updated unless you save in IP10.

You can test just by creating a plan and go to IP10 execute the scheduling, now go to MHIS table and check, will not give any output.

After you save, then it will be updated.

I guess your requirement cannot be done via standard options, you need to develop or get the similar code as IP24.