Organising transport targets when two source systems and one target system

Former Member
0 Kudos

Hi,

we have the following situation.

In our SAP environment we have in this case for DEV two ERP systems, which are connected two one PI system.

In QA and PROD there is only one target system. We want to organise our SLD landscape and transport management in this way, that there is an automatic mapping while transporting. We don't want to configure manually the Integrated Configuration and delete the obsolet business system.

Does anybody has a solution for this issue?

The thing is, we want the transportation process with less manual configuration, because we use CTS+.

Otherwise as i know every business system which should be transported, should have a transport target in SLD, but in our case there are two system which should have the same target system. From my experience this does not work.

DEV     QA     PROD

DEV1-->QA-->PROD

DEV2-->QA-->PROD

I hope, the explanation was comprehensible.

Thank you and kind regards,

Ronny

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member182412
Active Contributor
0 Kudos

Hi Ronny,

It is possible you can configure it like below in SLD. We already using same setup in our project and they are working.

DEV1-->QA-->PROD

DEV2-->QA-->PROD

Regards,

Praveen.

Former Member
0 Kudos

Hi Praveen,

thanks for your quick reply.

We will make a proof of concept, then i will close the discussion.

Kind regards,

Ronny