Sales order confirmed

Former Member
0 Kudos

Hi SD gurus,

i have created sales order and confirmed qty showing the date is 03/12/2015,and automatically updated the Purchase requisition no also updated in sales order item level scheduling tab.

one job to create the PO with reference  PR, but when I checking the delivery date is 03/12/2105 but goods issue date  is showing the wrong date 03/09/2105 in sales order level, but it should be showing the same date only in sales order,

why it showing the different dates, may i know the reason and please let me know.

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member223981
Active Contributor
0 Kudos

To me, your dates look correct:

Delivery Date = 12th March

GI Date = 9th March

According to the description of the route, the route takes 3 days. 12th - 3 days = 9th March. So the material should leave your shipping point on 9th to get to your customer on 12th. The transit time of the route is maintained in transaction 0VTC.

Hope this helps.

Former Member
0 Kudos

Hi

Can you please paste your below dates from Shipping tab .

Delivery date         D  

Goods issue date         

Loading date             

Material avail.date      

Transportation Plan. Date 0

Regards

Santosh