assuming that the preparatory steps for a migration to Simple Finance have been completed successfully and assuming a migration from Classic GL, how long approximately will the business downtime of the productive system be?

Best regards

Lutz

Accepted Solutions (1)

Accepted Solutions (1)

Arnaud
Employee
Employee
0 Kudos

Hi Lutz,

You can expect a minimum of 24 hours of production system downtime.

For example, for an actual migration we did, we experienced the following figures:

Data transfer (93 millions rows): 50 mns

Data migration: 11h elapsed time

Overall the elapsed time repartition should roughly work out to be:

Technical install: 10%

GL -> new GL: 30%

sfin data migration: 50%

activate NAA: 10%

Hope it helps,

Arnaud