on 02-27-2015 11:31 AM
Hi-
assuming that the preparatory steps for a migration to Simple Finance have been completed successfully and assuming a migration from Classic GL, how long approximately will the business downtime of the productive system be?
Best regards
Lutz
Hi Lutz,
You can expect a minimum of 24 hours of production system downtime.
For example, for an actual migration we did, we experienced the following figures:
Data transfer (93 millions rows): 50 mns
Data migration: 11h elapsed time
Overall the elapsed time repartition should roughly work out to be:
Technical install: 10%
GL -> new GL: 30%
sfin data migration: 50%
activate NAA: 10%
Hope it helps,
Arnaud
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.