Can we create a new SNP Production Horizon?

Former Member
0 Kudos

Hi,

I need to create in SNP:Supply profile (TX: /SAPAPO/MAT1), a SNP Production Horizon for WEEK, but I need that this Period Type for SNP Production Horizon start from Saturday. I just see from Sunday and from Monday. Somebody know if it is possible and how I do it ?

Best regards,

Ely

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hello Eliana,

Please use period factor in the product master to achieve this requirement. Try period factor 0.9 or 1.

Thanks.

Regards, Marius

Former Member
0 Kudos

Hello Marius,

thanks!... I tried to do that, but I can because the decimal places are not permitted.

Regards,

Eliana

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello Eliana,

Period Factor is in Lot size tab of product mater if decimal places  is not working then you can try comma, 0,9. Also you need to activated the Use period factor indicator.

Best Regards,

R.Brahmankar