on 02-25-2015 11:22 AM
For specific warehouse for an inbound delivery, WT is created and confirmed and GR is posted successfully. But still the putaway status in inbound delivery is set to "Not Started" and GR status set to completed.
Vice-versa GR posted before putaway, same problem exist in status update for putaway.
Hi Lakshmi,
Just check for the "Final Putaway Completed" confirmation check box in the storage type settings. Sometimes when we use POSC or LOSC, we don't set the putaway completed in case of intermediate storage type.
If checkbox is not checked then just check it if that is your final storage type and then try to post GR/Putaway again.
Thanks,
Sandip
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sowntharya Lakshmi
If is it happening for any specific delivery type, If yes please check status profile for header document type.
Regards
Suraj
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
can you check SMQ2?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Lakshami ,
Only GR status gets updated in R/3 . Why do you want to see putaway completed in R3 when EWM is used for warehouse management .
Regards,
Rajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.