on 02-24-2015 12:20 PM
Hi Gurus
I am working on a small demo for IBP supply.
Objective : Heuristic run in IBP
I have some questions regarding the same.If any of you have done this already, pease provide some guidance or documentation for the same.
Thanks, any help would be highly appreciated.
Lavi
Hi Lavi,
Patrizia has already responded on inputs required for the Unconstrained heuristic in terms of Master Data and Input Key figures. Thanks Patrizia!
In addition, If you are not modeling any capacity you don't need to model Source Production, Production Source Item (BOM), Production Resource master data types and associated key figures such as PCAPASUPPLY, PCAPACONSUMPTIONRATE.
You can also just advance copy delivered SAP4 supply planning model and use this model.
Hope this helps.
Thanks,
Pramod
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Lavi-
I see there is a detailed answer for you question, but I want to clarify a couple points.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Lavi,
I’m doing the same.
I was able to copy SAP2, activate it, load some data and run heuristic.
I suggest you copy SAP2 because to start from scratch would be very long. I copied also master data type changing the prefix from S2 to my prefix.
Prerequisites for heuristic:
Use attributes PRDID, CUSTID, LOCID, RESID without changing their name (if you copy SAP2, even if you change the name of the master data type while copying, the attribute names will remain the same, so you should be ok).
Master Data needed
Products, Customers, Locations, Resources, Resource Locations,
Customer Source, Location Source, Production Source, Production source item (BOM), Production Resource (production cycle).
Key figures:
If you see in SAP2 the KF that are marked as Input and/or output for supply are those you should have.
Input key figures should be: consensus demand, inventory target, stock on hand, and the key figures corresponding to the above master data if you load master data as time dependent.
Output KF should be: all the dependent demand key figures (customer, location, production, dependent demand); net demand, capacity demand.
Capacity usage, all the receipt kf (customer, production, external, transport, total), all the supply KF, projected inventory.
Cheers,
Patrizia
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.