BPM deployment error

Former Member
0 Kudos

Hi,

I am facing following error while deploying the BPM object from NWDS. I have developed simple scenario file to file through NW BPM (AEX-BPM-AEX).

"Synchronous process of active pool "pool" must have exactly one message end or message termination event, but can have any number of end error events".

NWDS version - SAP Net Weaver Developer Studio, SAP Enhancement Package 1 for SAP Net Weaver Developer Studio 7.3 SP14 PAT0000

PO version - NW731EXT_14_REL

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos


Hi Osman,

Yes it is with AEX only i.e. with PO.

Now the issue is resolved after I have changed the event end step to message end step.

Regards,

Ramesh

Answers (2)

Answers (2)

Former Member
0 Kudos

Hello,

It seems that u are assigning multiple outgoing sequence to your (automated) step?

Thanks

Amit Srivastava

Former Member
0 Kudos


Hello Amit,

Automated activity is assigned to end event that's it.

BPM is simple => start step -> Automated activity (send step)-> end step.

Kindly suggest.

Regards,

Ramesh

Former Member
0 Kudos

Hi Ramesh

Check in the problem view for Error. You might see the error there and use Quick Fix if available.

Check if potential owners are assigned at all the task/process level.

Also check the input and output mappings of all the task.

Regards

Osman

Former Member
0 Kudos


Hi Osman,

I have pasted the error from problem view only.  It is simple BPM i.e only one send step nothing more than that.

I don't understand, Do we still need this "Check if potential owners are assigned at all the task/process level."  ? If so Please let me know how to do it.

Regards

Ramesh

Former Member
0 Kudos

Can you provide more details

You have mentioned that its a simple bpm (Start --Automated activity -- End)

Are you triggering this BPM from PI interface??

What Service Interface/WSDL did you used in Start trigger event? (Sync/Async)

Regards

Osman