cancel
Showing results for 
Search instead for 
Did you mean: 

Unit Cost Planning

Former Member
0 Kudos

Hello Experts,

While performing unit costing by CJ40, I maintained Category-M for material, material number, plant , Quantity in the line item, but I face the following error. -  No price could be determined for material/batch xxxx / plant xxxx . ( which is generally due to valuation field/class not maintained in the accounting view). Here, the scenario is of split valuation wherein each material in same plant has 2 entries as shown below, ( MM60 report screen )

Kindly suggest a proper way out for this scenario as this issue will also be seen during assigning material components.

T&R.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Supriya,

Check the Valuation variant settings in the Costing Variant defined for Unit Costing.

Define material Valuation in the desired sequence.

Secondly in txn OBYC, check setting for transaction BSX >> valid G/L account must be maintained against valuation modif. & valuation class (of the material).