Need to change the priority of the PDS during CIF. Please suggest the BADI which can be used in ECC side.I guess BAdis /SAPAPO/CURTO_SNP and /SAPAPO/CURTO_CREATE.can be used in APO. I need to change PDS value in ECC side while doing CIF or CURTO_CREATE..
With thanks & regards,
naveen
Hi Naveen,
As far as I know, in ECC the PDS is represented by the Production Version.
We don't have a priority to be assigned directly in the Production Version in ECC. The PV determination in ECC can be managed by the locking indicator, the lot sizes, the validity periods and the sequence in which the PV was created.
It can be possible to assign a priority thru a Quota Arrangemenet.
Production Version Selection - Process Orders (PP-PI-POR) - SAP Library
Kind Regards,
Mariano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mariano,
Like how the PDS is maintained in PDT_MAINT using the production version maintenance, where using the change option priority is changed, I want the similar option to be done through an enhancement while importing to APO either while doing CIF or CURTO_CREATE.This is to give priority to PDS than PPM.
With thanks & regards,
Naveen.
Hi Naveen,
Check this thread, here you have the solution:
http://scn.sap.com/thread/471898
Kind Regards,
Mariano