on 02-19-2015 3:28 PM
Dear PS Experts,
How can i create settlement rule automatically wbs project A to wbs project B (Actual Cost) .
I try to set settlement rule like a
settlement sender : WBS (project A)
settlement receiver : GL(Can refer WBS (project B) or not?)
After than try to CJ88
But Actual Cost can't show in project B
Please help.
1. Can set settlement receiver with GL + WBS or not?
2. I need to Settlement Actual Cost form project A to project B ,Please help to suggest how?
Regards
Nitha
Hello,
I would assume you need WBS (project A) to WBS (project B) settlement. No point to use GL account as settlement receiver.
Why settlement rules to be generated automatically? Is it a repetitive process for many pairs of projects? Would be nice if you can give a business case.
Regards,
Paulo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Nitha,
You can settle cost from One Project to Another. But this will require a small development. In std. auto generation of settlement rules in SAP PS, you can settle to superior WBS within a Project.
You would need help of a technical person to achieve it..
from the functional side make sure that your Settlement Profile allows settlement to the WBS and GL as valid receivers..
Hope it helps..
Regards
Sammar.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
11 | |
6 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.