on 02-19-2015 5:37 AM
Hi All,
Just curios to know that if anyone has tried Event based Message processing in Single Stack or PO.
Please share the configuration steps.
Warm Regards,
Rudra
Hi Rudra ,
I have not heard of it. However you can control message processign using Adapter availibility planning in single stack to start and stop channels at a particular time in a day.
Further you can also control channel start & Stop externally as well using ABAP program.
You can use this ABAP code to trigger message processing. I dont think there is some functionality in PI itself for this.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.