Former Member
0 Kudos

Hi Gurus,

I am looking for a solution where the ECC and APO dates for an STO should match. In ECC the STO is scheduled based on route (as per our setting) and APO is scheduled as per transportation lane.

Our transportation lane data is not accurate. So we want APO to adopt ECC dates. Is there an option for adopting ECC dates for STO.

If not I am looking for syncing Tlane duration from the routes. Can you recommend an option for this.

Thanks,

Gijoy

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Gijoy,

Normally CCR is able to see the STO's time difference between the two systems. So, it's up to you to send the ECC time on APO side or vice versa.

Thanks.

Regards, Marius

Former Member
0 Kudos

Hi Marius,

Thanks for your reply. CCR will not clear if there is a date mismatch if you schedule ECC based on routes and APO based on Tlanes.

Also I am not looking at a fix using CCR. When system creates the STO in APO, the dates should match rather than fixing everytime with CCR.

Thanks,

Gijoy

Former Member
0 Kudos

Hi Gijoy,

Maybe with this enhancement you can do what you want;  CIFPUR01

Thanks, Marius 

From SAP Help:

Transfer Customer-Specific Purchasing Data

Use

You can use enhancement CIFPUR01 to transfer purchase requisitions, purchase orders, and confirmations to SAP APO or to change existing data.

For more information, see the documentation for enhancement CIFPUR41.

Answers (0)