cancel
Showing results for 
Search instead for 
Did you mean: 

BRF Process level determination

former_member206441
Contributor
0 Kudos

Dear Experts,

We are using Process controlled Workflow. We created a process schema ZSC_PL_SCHEMA_SER with process type A and Task id 40007953, But at run time while debugging, the system is picking process type C and Task id 40007952, the Schema is same as ZSC_PL_SCHEMA_SER. I am not able to track that, how is different process type and Task id is picked for the schema.

Please give me some guide line.

Thanks & Regards

Arun.K.P

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Arun,

Did you create events and expressions for process schema evaluation to guide your workflow to corresponding schema definition?

You can go to SPRO -> SAP Implementation Guide -> SAP Supplier Relationship Management -> SRM Server -> Cross-Application Basic Settings -> Business Workflow -> Process-Controlled Workflow -> Business Process Configuration -> Define Process Levels

Then you can verify your Process Schema Evaluation and Process Schema Definition. Select corresponding Definition go to Process Level Configuration on left menu. Please re-check level type and task ID for all level sequence number.

Run it again and trace it in SLG1 for correct evaluation and tasks.

Hope it helps,

Daniel Demetrio

Answers (0)