on 02-17-2015 8:16 AM
Dear All
I am upgrading SAP Solution Manager7.1 sps 04 to current level using SUM tool.
Phase in SUM "PREP_INSTALL/RUN_RSDBSCPY_INIT" & background job "RSUPG_PARCLONE" is running over 1 day.
Clone is created in MMS but disp+work is stopped, clone instance service is running. Files under .../sum/abap/tmp & log is not updating except one file i.e., RSDBSCPY.
For reference, please see attached file for RSDBSCPY from .../sum/abap/log.
Please help me to resolve the issue.
Thanks & Regards
Ahsan
Hi Ebad,
Kindly check the sapnote 1351543 - Fixes for EHPI Toolimport
RSUPG_PARCLONE waits 10 seconds and checks the DBCLONE jobs.
If one succeed and one fails, RSUPG_PARCLONE goes into an endless loop.
- Checked the DBCLONE<n> job
- If the job is getting failed or getting restarted then try to fix the error.
With Regards
Ashutosh Chaturvedi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Do a "Check Status" for the job RSUPG_PARCLONE from Tx SM37 and see if the status of the job changes. Supply the OS and DB details.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
84 | |
10 | |
10 | |
10 | |
7 | |
6 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.