Dear SAP Expert,
Please advice.
We have requirement to do sales pricing in DP81 with project and inquiry.
Some steps that we are doing :
1. Create Inquiry : VA11
2. Create Project : CJ20n
3. Create cost planning with network activity in CJ20n and use Planning cost version 1. ( We are trying to use more than 1 version, not only version 0)
4. Run DP81. It shows error message no expenditure.
In the config ODP1 ( DIP Profile) , version has been activated.
Is there any solution to use ECP with version more than version 0?
Appreciate for the advice.
Thank you.
Nies
Hi Denis,
Only by selection version as a characteristic will not help. There is an user exit available for DIP profile, you have to use the exit to have sales pricing based on the cost planning done in CO version other than '0'.
Regards,
Akhil Rathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Denis,
Check your DIP Profile config.
might be something is missing related to Easy Cost planning. in sources you have to elect easy cost planning and selection criteria would be version 001.
thanks
Sunil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
ECP can not use standard version as 0 so as you said you have more then one version in your system so use version other then 0 while running business transaction.
Regards,
Sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.