Easy Cost Planning version >0 cannot be used in DP81

niessap
Discoverer
0 Kudos

Dear SAP Expert,

Please advice.

We have requirement to do sales pricing in DP81 with project and inquiry.

Some steps that we are doing :

1. Create Inquiry : VA11

2. Create Project : CJ20n

3. Create cost planning with network activity in CJ20n and use Planning cost version 1. ( We are trying to use more than 1 version, not only version 0)

4. Run DP81. It shows error message no expenditure.

In the config ODP1 ( DIP Profile) , version has been activated.

Is there any solution to use ECP with version more than version 0?

Appreciate for the advice.

Thank you.

Nies

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi Denis,

Only by selection version as a characteristic will not help. There is  an user exit available for DIP profile, you have to use the exit to have sales pricing based on the cost planning done in CO version other than  '0'.

Regards,

Akhil Rathi

niessap
Discoverer
0 Kudos

Hi Akhil Rathi,

You are right. It seems that Sales Pricing DP81 cannot read the planning cost in version more than 0. Do you have idea  the user exit for this scenario ?

Cheers,

sunil_yadav2
Active Contributor
0 Kudos

Hi Denis,

Please try below Enhancement:

KSDIEX01-     Determining expenditures in resource-related billing

hope this will help you.

thanks

Sunil

sunil_yadav2
Active Contributor
0 Kudos

Hi Denis,

Check your DIP Profile config.

might be something is missing related to Easy Cost planning. in sources you have to elect easy cost planning and  selection criteria would be version 001.

thanks

Sunil

niessap
Discoverer
0 Kudos

Hi Sunil,

As per my previous attachment. I have maintained ECP and version 001 in DIP Profile, but in DP81 cannot read the planning cost in version 1.

Cheers Sunil.

sanjeevc
Active Contributor
0 Kudos

Hello,

ECP can not use standard version as 0 so as you said you have more  then one version in your system so use version other then 0 while running business transaction.

Regards,

Sanjeev

niessap
Discoverer
0 Kudos

Hi Sanjeev,

Sales Pricing (DP81) can read ECP with standard version 0. The issue is that DP81 cannot read version other then 0.

I need to do planning cost using version other than version 0 ( Actual/Planning version)

Thank you for your advice.