on 02-13-2015 5:00 PM
Hi Experts,
We have a situation where in the the PReqs in ECC are calculated in
past.
We have an example where by there was a requirement at C079 on 24th
February. There is GR Processing time of 5 days maintained at C079 and
transport duration of 24 minutes. After running deployment, a
Distribution Demand (Confirmed) was created on the source, C061 on 19th
February and a Distribution Receipt (Confirmed) was created on C079 for
24th Feb. This, we believe is as expected.
Now, in ECC we are able to see a PReq at C079 on 24th Feb, but the
corresponding PReq on C061 is showing on 2nd Feb in MD04. We need to
understand that as to why the PReq at C061 has been created in past.
Please note that there is a Planned Delivery Time of 17 days maintained
at C079. We understand that this should not cause any issue, but please
take a note of it.
Please advice. Thank you.
Regards,
Rishi
Dear Rishikesh,
It appears that the Purchase Info record in R3 and the Tlanes in APO are different. In APO the PR is picking the Tlane period but once its ciffed to R3 the PR time is recalculated . In standard if you have a Tlane in APO then the PDT is ignored or overwritten in APO.
The recalculation happens by fixing the availability date. Please ask your developer to debug if you have any exit or code which is influencing the behavior.
I would also suggest you to maintain the Transportation Duration in APO for atleast 1 day i.e. 24Hrs. The minimum bucket of planning in SNP is a day.
Thanks and Regards,
Gajanan Patki
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
For the benefits of the others consultants, please indicate the good or the helpful answer!
Thanks, Marius
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I think you have a problem with the planned delivery time in ECC and the time from the transportation lane in APO.
Remove the planned delivery time in ECC, ensure it is also deleted in MAT1 and re-plan your code.
Also take a look of this thread:
And check these notes:
379006
- Transport duration and planned delivery time in APO and R/3
441622
- Supplying-plant-dependent planned del. time/trans. time
Kind Regards,
Mariano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This certainly looks like a misalignment of one of the processing times between APO and ECC.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Rishi,
Why are you supposing that Planned.deliv.time (C079) doesn't have any influence on the delivery date at source location level (C061)?
Please see below (from SAP help).
Thanks, Marius
Number of workdays required to acquire the product or service using external
procurement.
The system uses the supplier location's production calendar to determine the
planned delivery time. If a production calendar is not defined at the supplier
location, the system calculates the planned delivery time in calendar days.
If you have various suppliers for a product, you have to specify an average
value. This also applies if you always order the product from the same supplier,
but the supplier's delivery times vary.
The planned delivery time is used differently in heuristic-based
planning and optimization-based
planning:
The system only takes into account the planned delivery time if there is no
source location for external procurement.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.