Enhancement implementation must still be adjusted Syclo WM 6.2

CRVMANISH
Contributor
0 Kudos

Hello Experts,

I did the BADI enhancement for notification and work order in syclo. While transport it is asking for Enhancement adjustment. What is the best practice to do it and how it should be done?

I have attached screenshot for reference.

Regards

Manish

Accepted Solutions (1)

Accepted Solutions (1)

Marçal_Oliveras
Active Contributor
0 Kudos

Hi Manish,

When you create a new BADI implementation SAP expects you to create each method.

Basically you have to double-click each BADI implementation class method, and if you don't want to execute anything there, just leave it empty. Once you created all the methods, activate the class and the error will disappear.

former_member2126
Discoverer
0 Kudos

Hi marshal.oliveras2

Thanks it helped me a lot.

Answers (2)

Answers (2)

i834235
Product and Topic Expert
Product and Topic Expert
0 Kudos
former_member194451
Active Participant
0 Kudos

You question gear more toward ABAP development practice. You should check this type of question under SCN ABAP community for best practice. It is pure ABAP development issue.

Regards,