Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

CM25 - wrong scheduling for external operation

Hi all,

I have e problem in plannig table for external operation. The system (only for external operation) schedule order also on holidays  (as if they are working days).

Below an example to better explan the problem:

The order have scheduled finish date on Sunday 22/02/2015 at 24:00 (not working day).

Can someone help me? There are specific settings in the profile?

Thank You,

Best Regards,

Giuseppe Caselli

replied

Hello,

If the operation is defined as an external processing operation, the system displays and takes the planned delivery time as the processing time into account. The operation is scheduled with the planned delivery time according to the Gregorian calendar.

As of Release 4.0, you can also schedule externally processed operations with formulas at the work center. For this, indicator "Scheduling external operation with standard values" must be activated in the respective control key. In this case, the planned delivery time is not taken into account. Please check the same.

Best Regards,

R.Brahmankar

0 View this answer in context
Not what you were looking for? View more on this topic or Ask a question