CM25 - wrong scheduling for external operation

zgius16
Participant
0 Kudos

Hi all,

I have e problem in plannig table for external operation. The system (only for external operation) schedule order also on holidays  (as if they are working days).

Below an example to better explan the problem:

The order have scheduled finish date on Sunday 22/02/2015 at 24:00 (not working day).

Can someone help me? There are specific settings in the profile?

Thank You,

Best Regards,

Giuseppe Caselli

Accepted Solutions (1)

Accepted Solutions (1)

zgius16
Participant
0 Kudos

Hi Rupesh and Kiran,

the work center is marked for fine scheduling and setted whit a valid FC. In the overall profile "planning in non-work periods" in not flagged.

Do you have other suggestions?

Best Regards

Giuseppe

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

If the operation is defined as an external processing operation, the system displays and takes the planned delivery time as the processing time into account. The operation is scheduled with the planned delivery time according to the Gregorian calendar.

As of Release 4.0, you can also schedule externally processed operations with formulas at the work center. For this, indicator "Scheduling external operation with standard values" must be activated in the respective control key. In this case, the planned delivery time is not taken into account. Please check the same.

Best Regards,

R.Brahmankar

zgius16
Participant
0 Kudos

Great! It works perfectly!

Rupesh, thanks for the help.

Regards,

Giuseppe

Answers (2)

Answers (2)

kiran_kumar179
Active Contributor
0 Kudos

Caselli,

It might be because it is considering the planned delivery time which considers calendar days not factory calendar days.

So try with assigning a valid FC in capacity header tab of external processed operation work center.

BR
KK

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello Giuseppe,

Does your work center for external operation mark for finite scheduling?

It should have valid factory calendar assigned in work center capacity tab with valid shift schedule.

In the strategy profile of the overall profile used for capacity leveling,  check if you have set the flag, "Planning in non-work periods.

Best Regards,

R.Brahmankar