Hi All,

  User is getting an error saying " Action could not be performed, status UPDATE is still in process" while editing PO in SRM. There were some changes been done by user on 2/3/15 for which the cart was awaiting approval and i didnt see any work item triggered for that approval. So, I have pushed the PO from SRM to ECC via FM BBP_PD_PO_TRANSFER_EXEC and all the changes reflected to ECC and status of the PO in BBP_PD changed to document completed (I1180). After this i tried to edit the PO in EBP, got the same message. Then i ran CLEAN_REQREQ_UP, BBP_GETSTATUS_2 but nothing is changing the PO status in SRM.

  Can you please share some tips on this.

Regards,

Prasad

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi All,

  Can you please suggest some solution for this problem.

Regards,

Prasad