cancel
Showing results for 
Search instead for 
Did you mean: 

/TMWFLOW/SCMA_BTCH_SYNC_TEST and Normal Change

Vivek_Hegde
Active Contributor
0 Kudos

Hi,

Can we modify the program /TMWFLOW/SCMA_BTCH_SYNC_TEST in a way to import completed Normal Changes to multiple clients in a Test and Production System?

Have any of you tried importing Normal Change corrections to multiple clients in Test and Production systems in an automated way?

Regards,

Vivek

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Vivek,

you can use Transport group if you have multiple clients, but either or the way you have to do the import of NC. have you tried with task list, automatic schedule jobs?

we need sync job only for UC, since UC follows the shortest route to PRD, for NC you have to import manually or with scheduled jobs,

Hope this helps

Thanks

Jansi

Former Member
0 Kudos

Hi Vivek

Would /TMWFLOW/SCMA_BTCH_SYNC_UC not do the trick for you (schedules to run periodically to get the UC in Production)? Also, refer to note  817289 for more guidance.

Regards

Rob