Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

Calculation of goods receipt time between R3 and APO

Hi Gurus,

I have a question regarding scheduling of goods receipt time between APO and R3. I found a production order
in R3 which has a basic finish date at 13.02. + 2 days goods receipt time.
In APO I maintained of
course a handling resource for the location for goods receipt with a workday calendar and 24h capacity.

In R3 I see the receipt day is the 17.02. (13 + 2 + 2 (weekend) ).

In APO I see as the receipt day 15.02. (no weekend considered)

My questions:

Is there a further setting I have to setup at the handling resource in APO to consider only ‘working
days’ of my defined plant calendar?

Thanks for your help!

Best Regards

Julian Peer

Former Member

Helpful Answer

by
Not what you were looking for? View more on this topic or Ask a question