Calculation of goods receipt time between R3 and APO

Former Member
0 Kudos

Hi Gurus,

I have a question regarding scheduling of goods receipt time between APO and R3. I found a production order
in R3 which has a basic finish date at 13.02. + 2 days goods receipt time.
In APO I maintained of
course a handling resource for the location for goods receipt with a workday calendar and 24h capacity.

In R3 I see the receipt day is the 17.02. (13 + 2 + 2 (weekend) ).

In APO I see as the receipt day 15.02. (no weekend considered)

My questions:

Is there a further setting I have to setup at the handling resource in APO to consider only ‘working
days’ of my defined plant calendar?

Thanks for your help!

Best Regards

Julian Peer

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Julian,

You have maintained Time stream in the location master under "calendar" tab the production calendar and warehouse calendar, and handling resource in the Resource Tab?

how have you generated your time stream?