SAP note 955107 - Purchs req commitmt not to be taken into accnt in avail.ctrl

Former Member
0 Kudos

Hi

We have implemented SAP note 955107 . We are creating PR using networks and activities  in Project system that is account assignment N .  The system is still considering  PR Commitments in avail. Ctrl.

If the account assignment is P in PR  the system is not considering PR commitments in avail Ctrl.

Any corrections is required  if account assignment is N in PR please suggest

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi

I executed the transaction CJEN, CJBN still we are facing the same error. I think this note does not work for PR created with account assignment N from projects. Can you test and confirm whether it is performing the same way in your system.

i have also raised a OSS  note for this

Regards

Vijay Kumar Hebbal

Former Member
0 Kudos

Hi Vijay,

Did you implement the correction instructions from note 955106 before implementing the note 955107?

Alternatively, you can also refer the notes below and see if they help you solve your issue,

1307755 - Deactivate update of purchase requisition commitment

2120564 - Deactivate update of purchase requisition commitment


Regards,

Gokul

former_member384980
Participant
0 Kudos

Requesting to Run t-code CJEN & CJBN for all the Projects and then check once again. If not raise this issue to SAP.

Regards

Deepak