XML Error during contract creation in ECC "Enter a Unit of Measure"

pratap_jk
Active Participant
0 Kudos

Hello Experts,

Need your advice on the above issue.

Contract is being created from Independent Rfx and the XML is successful in SRM, but getting stuck in ECC with Error as


Material UOM is KG and it is maintained in both the systems.

ISO Code is KGM. There are no Duplicates in both the systems.

Still we get the above error.

Please give your valuable suggestions to fix this issue.

Regards

Pratap

Accepted Solutions (0)

Answers (1)

Answers (1)

ivy_li
Active Contributor
0 Kudos

Hi Pratap,

Would you please check if the following note would help?

1851316 CCM: VK 022 - Enter a unit of measure

This is a MM issue instead of SRM, and you have to check customizing in MM side if the above note doesn't work.

Best regards,

Ivy