on 02-05-2015 8:38 PM
Hello Experts:
In transaction CFM1, you can send the PDS to SCM either by selecting the PDS(ERP) or BOM. I was wondering if you can shed some light on the differences if any. My only objective is to send a PP/DS PDS to SCM. I also attached a screen shot of both of these options. I am using a SCM 7.0 EHP3.
Thanks,
Satish Vadlamani
Hi Satish,
If you want to send the PDS you have to select just option PDS without BOM. The PDS will be created on APO side with the components that you have already send in APO in the precedents steps. So, you don't need to plan all levels of the BOM in APO. You can plan just critical components!
The combination PDS and BOM you can use it if you have Sale BOMs or Phantoms. It's preferable to use them separately!
Hope that can help you!
Thanks.
Regards, Marius
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
For the benefits of the others consultants, please indicate the good or the helpful answer!
Thanks, Marius
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Satish
Firstly you need to understand how Bom Explodes
Example : Assume you have Material X to manufacture X you required X1 X2,X3 .so now your Bom is 4 level .But you dont want to explode all 4 levels .to avoid this you combine x1,x2,x3 has Y by setting Phantoms assembly off . so now you are explodes in 2 level
If phantoms assembly is OFF (i.e 2 level ) you can go with selection of PDS directly by selecting PPDS
But if you want to explode each component in PDS(i.e 4level) then we will go for BOM
Only activation of integration model does not transfer PDS to APO .After activating PDS in APO yo need to go Initial transfer By using TCODE : Curto_create . you need to insure integration model of pds is active
and all the BOM and Routing are correctly mantained in material master in ECC
I hope this could help you in understanding
Regards
Virender
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Satish,
Option one you can use to send PPDS PDS to APO. It will CIF the production version to APO which include the BOM too.
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.