Hi,

Since the EM is integrated with TM and ECC hence can you let us know if we update the loading/unloading/PGI date etc in ECC, is there a mechanism by which the same dates can be automatically updated in TM Ececution node also. If not, what can be the way around to update the above events in TM execution node as well.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Dipak,

You have to be more clear on explaining your scenario.

Let us assume that you are tracking a Freight Order, which is DTR (delivery transportation requirement) based integration between ECC-TM.

The DTR should have the dates which then can be mapped to the stages/stops data on the Freight order. Thus, the expected event extractor should read the data from the STOP table.

So now, if the TM-EM integration is set up properly, you should see the dates and expected events on the execution tab of the Freight Order.

----

Now, when you say update the loading/unloading/PGI date etc, did you mean updating on the Shipment in ERP ? if yes, the SHPMNT05 should push the dates to TM and update the Freight Order.

An update of the Freight Order should trigger EM and via the extractors the same dates should be updated in EM as well.

-----