FM Period Closing for Particular Fund and Fund Centre

Former Member
0 Kudos

Dear Expert,

Can we block the FM period for the particular Fund/Fund Centre instead of opening it for particular account assignment and values ?

Regards,

Prad Pat

1 ACCEPTED SOLUTION

iklovski
Active Contributor
0 Kudos

Hi,

Not by standard means. FM standard functionality allows to open periods not to block them. So, indirect blocking will be realised when you open periods for all combinations except for the one you want to block.

If it is front end FI documents which will be posted for this FM assignment, the easiest way to block them would be writing validation in FI.

Regards,

Eli

View solution in original post

2 REPLIES 2

iklovski
Active Contributor
0 Kudos

Hi,

Not by standard means. FM standard functionality allows to open periods not to block them. So, indirect blocking will be realised when you open periods for all combinations except for the one you want to block.

If it is front end FI documents which will be posted for this FM assignment, the easiest way to block them would be writing validation in FI.

Regards,

Eli

Former Member
0 Kudos

Thanks Eli..

Regards,