Hello all,


Please find below my issue and my request :


SAP ECC6


Aim: Create several QM batch for the same goods entry

Assumption: I create a PO for a quantity of 1000. My material is expected to be controlled and has got a QM view

Why do I want this ? : the target is the possibility to release the goods entries (goods mouvement quality inspection > unrestricted used) units as soon as the material is controlled (i.e. gradually) and not wait that the control of the whole sample is finished, in order not to penalize the assembly of finished products at the end of assembly line (finished products manufactured with semi-finished products controlled in QM)

My issue : When doing my MIGO, the system creates a unique QM batch for inspection and the quantity of my batch equals the quantity of the goods entries

For my case, goods entries = 1000, hence my QM batch + 1000

What I want: if for instance goods entries = 1000, I want for instance 10 batchs of 100 quantities created

What I have to do in the customizing to divide the goods entries in differents batch ?

Thank you very much for your ideas, suggestions or solutions !

Best regards

Vincent

Accepted Solutions (0)

Answers (1)

Answers (1)

krishnamurty_madduri
Contributor
0 Kudos

Hi,

Pl. try using these User Exits:

EXIT_SAPMM07M_010

EXIT_SAPMM07M_003

Regards,

KrishnaM