Hi All,
We have below 2 jobs running in our production system.
GRAC_SPM_LOG_SYNC_UPDATE
GRAC_SPM_SYNC
We have parameter 4007 set as YES
As per my understanding if 4007 set as YES, no need to schedule SPM Workflow sync job.
We have job GRAC_SPM_LOG_SYNC_UPDATE scheduled individually for each system.
What does this job GRAC_SPM_SYNC do? What is the difference between GRAC_SPM_SYNC and GRAC_SPM_LOG_SYNC_UPDATE ?
I tried to run both jobs in my system
1. GRAC_SPM_LOG_SYNC_UPDATE has the option to enter the connector name
2. GRAC_SPM_SYNC execute directly.
Can someone explain why this job GRAC_SPM_SYNC is required?
As we saw there are some Invalid log reports generated in our system, I doubt having these 2 jobs is creating issue where GRAC_SPM_LOG_SYNC_UPDATE is enough?
Experts please advise
Regards,
Nilkant
Hi Nilkanth,
GRAC_SPM_SYNC - EAM master data synch program - Used in case of De-centralized FF scenario
GRAC_SPM_LOG_SYNC_UPDATE - To Fetch the FF logs from Plug-in system
Invalid Log report reasons
1. Multiple background jobs of GRAC_SPM_LOG_SYNC_UPDATE running in background. Please check
Regards,
Madhu.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Nilkanth,
If you are using decentralize firefighting then to sync master data in plugin and GRC system GRC_SPM_SYNC needs to be scheduled.
GRAC_SPM_LOG_SYNC_UPDATE will sync the logs and then workflows.
There are few fixes recently related to invalid log review workitems:
-2100872
-2092348
-2066773
Thanks & Regards,
Chandani Kaur
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.