Transfer lost (APO-->R/3)

Former Member
0 Kudos

Hi,

I transfer my forecast from APO to R/3( just 1 material with 4 locations). When I checked SM37(APO side), it showed that my transfer was successful. However, when I check MD63 on R/3 side, I could see only 1 location ( supposed to be 4 locations). Does anyone know what's going on ? How could I check it on R/3 side whether my data came thru.

Thanks,

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Go to SPRO and search for "publication settings"

check if all four locations have been mapped for PIR transfer

Former Member
0 Kudos

Hi Harish,

Hope that you are doing well, I am Arun.Can you please tell where exactly find the publication settings,I would search in 4.7.But i am not able to find.

Thanks & Regards

Arun Prasath

0 Kudos

Publication settings are in SPRO in APO side not R/3 side.

Somnath

Answers (2)

Answers (2)

Former Member
0 Kudos

Thank you so much for your help. I awarded both of you points....

Former Member
0 Kudos

Hi,

Maintain the distribution definition for the 4 locations.

Thanks and regards,