How to have alternate source for time stream (calendar) while sales order ATP check?

Former Member
0 Kudos

Current Behavior: The Time stream source while ATP of the sales order is the location, which is, either plant (location 1001) or MRP Area (Location 1007).

Question: How can I have the time stream source as shipping point (Location 1003)

Requirement: The requirement is to have different shipping calendars depending upon the OLTP shipping point of the sales order.

This is to have, the In-house activities, such as picking/packing and loading, to be calculated based on this shipping calendar rather than the shipping calendar assigned in the location master

-!!Note: The shipping point has been included in the CIF model and have been activated.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Please check at location level on APO side, tab calendar.

Thanks.

Regards, Marius

Answers (2)

Answers (2)

Former Member
0 Kudos

Hello,

For the benefits of the others consultants, please indicate the good or the helpful answer!

Thanks, Marius

Former Member
0 Kudos

Kodand,

You normally would implement transportation and delivery scheduling in APO to meet these requirements.  Probably the simplest implementation is using Scheduling according to the Condition Technique.

Scheduling Using the Condition Technique - Scheduling - SAP Library

You can assign specific shipping calendars to the Shipping Points (which by the way are also considered to be locations).

Best Regards,

DB49