BOP Changed my confirmed Sales order MAD.

former_member610586
Discoverer
0 Kudos

We have enough stock to support the order item, and it is confirmed as GI on Jan 26th but it was pushed out to GI Jan 27th by BOP (/SAPAPO/BOP) every time when it executes.

sort profile..Delivery Priority, RDD,ERDAT

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Pravin,

GI date is usually dependent upon delivery scheduling parameters.  First thing to check is "what is the Material Availability Date".  I will assume you are strictly using a simple product check.  To start, show us a display of /SAPAPO/AC03  for the product/location/BE "A", select 'single records', and indicate on your screenshot the order that is of concern to you.

Best Regards,

DB49.