on 01-28-2015 1:16 PM
Hello,
When I create a work order and assign it to the Network Activity my basic dates are overwritten taken from the NWA.
Now imagine that I am not using SAP scheduling functionality, but need basic original dates that were entered manually.
Is it possible to supress the functionality of automatic dates inheritance from NWA to Work Order?
Thank you,
Hi,
Check the settings for Plant/Order type in transaction OPU7.Ensure the setting is 'Do not adjust basic dates, dep. reqmnts to operation dates'.
-Paul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Paulo
Another thing you may want to take a look at is a BAdi CAUFVD_CHANGE ("Overall Network Scheduling with Selection Option") which controls when and how the dates are copied from the Networks to the subnetworks (Work Orders in your case).
There is a method called "SET_ORDER_DATE" which can be used for this purpose.
Check this link and read the help document on this BAdi first.
Overall Network Scheduling with Selection Option - Dates - SAP Library
Cheers
Savas
User | Count |
---|---|
104 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.