cancel
Showing results for 
Search instead for 
Did you mean: 

CJCO do not calculate Actual amount

0 Kudos

Dear all

During CJCO run the program didn't take into account 2014 actuals. On specific WBS element we have some Assigned amound in 2014 (in CJ31), but in CJCO we have 0 in Actual column. As result, whole budget was carried forward to 2015 which is incorrect.

I've tried to reconstruct project info and availability control (CJBW, CJEN, CJBN), but it doesn't helped.

I've tried BPCARRYF report for analysis, but it returns error AP147.

Please advice what else can be checked?

Accepted Solutions (1)

Accepted Solutions (1)

0 Kudos

This was error in program. SAP issued correction 2124310.

Assigned points to myself ))

Answers (1)

Answers (1)

varshal_kachole3
Active Contributor
0 Kudos

Hi,

To undertstand the bahaviour of Budget Carryforward please refer http://service.sap.com/sap/support/notes/1048588

Hope it Helps!

Thanks and Regards,

Varshal Kachole